School Bond and Seismic Report
October
30, 2006
Contact
Larry LeDoux
481-2000
for Information
SEISMIC PROJECTS
The seismic projects are the Assembly's top priorities.
That aside, there is money to design the retrofit to this structure (see below) and we have proceeded. The architectural firm of Yorba, Jensen and Lott is under contract and is working on drawings. The middle school is the first structure to be reviewed, designed and repaired. Work is anticipated to begin in the spring of 2007.
·
Ouzinkie
Foundation. We received a State of
· Peterson Elementary. Funds to address the recommended seismic retrofits for Peterson Elementary have been identified. The Borough will issue a “Request For Proposals” (RFP) early this winter for design and engineering work.
·
Kodiak
Schools Non Structural Repairs - Staff is working on another State of
In addition to the grants that we have received from state agencies, the legislature has granted, and the Assembly has recently accepted, a $910,000 grant for undesignated seismic projects. Part of this allocation may be used as part of our 25% match requirement for the Federal FEMA grant. In addition, another $400,000 from the Assembly (originally from the state legislature) has been earmarked for our school seismic projects. These projects include KHS Gym Wall Retrofit and Peterson School Seismic upgrades
BOND PROJECTS - Completed Projects
BOND PROJECTS - RFP #1 and Staff working with Contractors
RFP #1 includes the following "Borough Hill" projects. The design of
these projects is being performed by the firm of Yorba, Jensen, and Lott. Those
projects not needing design work are staff projects. Staff is working with
contractors to complete the work (KMS Concrete and KHS HVAC):
BOND PROJECT - POOL
BOND PROJECTS #2
An RFP for design services (and selection of an Architect) will be going out this winter. The projects included with this RFP include:
OTHER BOND PROJECTS TO BE PERFORMED BY STAFF
LEGISLATIVE GRANTS
During the last legislative session, a number of grants were awarded to the school district. By legislation, this money (as well as audit and reporting requirements) has been directed to go through the Borough. Our druthers is to have the KIBSD perform most of this work. These projects include: